Hungarian network charges fall 43–55% for industry in 2027 – what it means for battery storage

MEKH published the 2027 system usage charges: the volumetric charge collapses, the demand charge falls by a quarter, the base charge doubles
November 19, 2026 by
Hungarian network charges fall 43–55% for industry in 2027 – what it means for battery storage
Alen Jaksa

On 16 November 2026 the Hungarian energy regulator MEKH published the electricity system usage charges that apply from 1 January 2027. On the voltage levels used by industry, the average network tariff falls by 43–55%. But the three parts of the bill do not move together: the volumetric charge collapses, the demand charge falls by about a quarter, and the base charge doubles. For anyone planning battery storage, that changes the calculation.

Executive summary (PDF)Try the payback calculator

What MEKH announced

According to the regulator, average charges fall significantly in most categories. The reasons are a more favourable price environment for buying network losses and balancing reserve capacity, and a more cost-reflective allocation of costs. MEKH expects the 43–55% reduction on industrial voltage levels to improve the regional competitiveness of Hungarian companies.

  • The base charge now includes the costs of metering, meter reading and customer service.
  • The regulator wants to strengthen the role of the fixed charges (base charge and demand charge) and reduce the share of volumetric charges. Fixed charges reflect the availability of the grid and encourage better capacity management.
  • During 2027 MEKH will continue to examine the role of fixed charges and time-of-use tariffs, and will decide after evaluating the results.
  • The normative connection fees for low- and medium-voltage consumption-side connections, practically unchanged since 2016, were reviewed: the coverage level is set at 24% for the connection base fee and 26% for the public line fee.
  • The special fees for administrative services mostly change with inflation.

The numbers: 2026 → 2027

The table shows the distribution charges for interval-metered users, from the tariff table of MEKH decision H 3193/2026, next to the 2026 values.

ConnectionBase charge (HUF / connection point / year)Demand charge (HUF / kW / year)Distribution volumetric charge (HUF / kWh)
High/medium voltage216,504 → 431,352 (+99%)8,004 → 7,020 (−12%)3.42 → 0.84 (−75%)
Medium voltage (KÖF)216,504 → 431,352 (+99%)15,924 → 11,868 (−25%)8.39 → 1.90 (−77%)
Medium/low voltage (KÖF/KIF III.)72,168 → 143,784 (+99%)16,608 → 11,688 (−30%)14.92 → 3.76 (−75%)
Low voltage, interval-metered (KIF III.)72,168 → 143,784 (+99%)13,248 → 12,756 (−4%)22.20 → 8.89 (−60%)

On top of this, every user connected to the distribution grid pays the transmission volumetric charge, which falls from 3.39 to 2.49 HUF/kWh. For a medium-voltage consumer the two volumetric charges together fall from 11.78 to 4.39 HUF/kWh, a reduction of 63%.

Example: a medium-voltage consumer with 1 MW and 4 GWh a year

In 2026 this consumer pays 63.3 million HUF a year in system usage charges: 16.1 million in fixed charges (base and demand) and 47.1 million in volumetric charges. In 2027 the same consumption costs 29.9 million HUF: 12.3 million fixed and 17.6 million volumetric. That is 53% less, in line with the range MEKH published.

The more important change is inside the bill. The share of fixed charges rises from 26% to 41%. Contracted capacity costs less in forints, but it now decides a much larger part of what the site pays.

What it means for battery storage

There are four effects, and they do not all point in the same direction.

  • Peak shaving is worth less per kilowatt. On medium voltage, one kW of contracted capacity saved is worth 11,868 HUF a year instead of 15,924. A storage system that lets a site reduce its contracted capacity by 200 kW saves 2.4 million HUF a year instead of 3.2 million.
  • Charging from the grid gets cheaper. The network charge on every kWh taken from the grid falls from 11.78 to 4.39 HUF on medium voltage, so charging and the round-trip losses of each cycle cost less.
  • PV self-consumption saves slightly less. A kWh that is stored and used on site instead of bought from the grid avoids about 7.4 HUF less in network charges than in 2026.
  • The spread stays. The network charge moves by a few forints per kWh. On 9 November 2026 the gap between the cheapest and the most expensive quarter-hour on HUPX was 420 EUR/MWh, more than 150 HUF/kWh. Arbitrage and aFRR remain the main revenue of a storage system.

In our published example of a 0.5 MW / 1 MWh system, the demand-charge item falls from 3.2 to 2.4 million HUF a year. Counting only this change, the conservative case moves from 20.3 to 19.5 million HUF a year and the payback from 4.7 to 4.9 years; the market-based case stays at about 3 years. You can already enter the 2027 demand charge in our payback calculator.

What to do before 1 January

  • Check your contracted capacity. With a doubled base charge and a 41% fixed share, capacity that is contracted but not used is the largest avoidable item on the network bill.
  • Recalculate any storage business case with the 2027 charges, item by item: demand charge, grid charging and self-consumption move differently.
  • Follow MEKH's review of time-of-use tariffs. If network charges become time-dependent, a storage system with price- and load-based control gains a further revenue source.

Send us your 15-minute load profile and your contracted capacity, and we show what the 2027 tariff changes at your site and for a storage system sized to it – free of charge.

Request a recalculation

Commercial & industrial energy storage – our solution page →

Sources: MEKH announcement of 16 November 2026 and the tariff table of decision H 3193/2026 (charges from 1 January 2027); 2026 charges: MEKH decision H 2995/2025. The example is illustrative and covers system usage charges only, without VAT, energy price and other bill items. Percentages for individual items are our own calculation from the published tariffs.

Read the MEKH announcement (in Hungarian) →

# News
Hybrid power plant control in practice: solar, storage and diesel genset in one logic
Priorities, operating modes, second-by-second decisions – and the typical mistakes of hybrid projects